At a glance. A well test flows a new, appraised or worked-over well through temporary surface equipment to measure its oil, gas and water rates, its pressures and the properties of its fluids. The results feed reservoir models, field development plans and production allocation, so the measurements and samples must be trustworthy. Operators and service companies across the world, onshore and offshore, use the same basic equipment train.

The equipment train

  1. Flowhead or wellhead with a surface safety valve tied to the emergency shutdown system.

  2. Desander, which removes produced sand before it erodes the chokes and piping.

  3. Choke manifold, with fixed and adjustable chokes that set the flow rate and drop the pressure.

  4. Data header for pressure, temperature and sampling points.

  5. Heater, which prevents hydrates at the choke and helps oil and water separate.

  6. Test separator: a three-phase vessel that splits gas, oil and water and meters each stream.

  7. Gauge or surge tank, used to check oil shrinkage and the separator oil meter.

  8. Transfer pumps and burners or flare, or a line back to production facilities where available.

What is measured

  • Flow rates of gas, oil and water, and from them the gas–oil ratio and water cut.

  • Pressures and temperatures for drawdown and build-up analysis.

  • Sand production at the desander.

  • H2S and CO2 content, which also decides the materials and safety measures.

  • Separator oil and gas samples for PVT analysis, often recombined to the measured gas–oil ratio, with bottomhole samples where needed.

Design points

  • Pressure rating for the maximum shut-in wellhead pressure, and materials suited to H2S service where needed.

  • Separator sizing for the expected range of rates, with metering suited to each phase.

  • Erosion from sand at high velocity, particularly at chokes and bends.

  • Hydrate control with heat or chemical injection.

  • Emissions and flare limits, which may set test duration or require the flow to go to production.

  • Sampling at stable conditions with suitable cylinders.

Common problems

  • Choke erosion when sand is not removed upstream.

  • Hydrates downstream of the choke.

  • Carry-over of liquid into the gas line or gas into the oil line, which spoils the metering.

  • Emulsions and foaming that make water cut and oil rate uncertain.

  • Samples that are not representative because the separator was not stable when they were taken.

Where Tech Inc. equipment fits

Related reading

This note is general guidance. Well test design follows the operator's procedures, the well data and the regulations where the test is carried out.