Process Note: Pre-Commissioning, from Flushing and Pickling to Pressure Testing

At a glance. New piping and vessels arrive with mill scale, weld spatter, oil and dirt. Repaired equipment after a turnaround carries scale and debris. Pre-commissioning removes all of this and proves the system holds pressure before process fluids go in. Most of the work is done by specialist contractors with mobile skids.
The usual sequence
Hydrostatic or pneumatic test. Each system is filled and pressurised to the test pressure in the code, held and inspected. A recorder produces the chart for the test package.
Chemical cleaning. Heated alkaline degreasers remove oil and grease; inhibited acids or chelants remove mill scale and rust; a neutralising rinse follows.
Pickling and passivation. Stainless and duplex piping is pickled to remove heat tint and embedded iron, then passivated to restore its protective oxide film.
Oil flushing. Lube, seal, control and hydraulic oil systems are flushed at high velocity and temperature until particle counts meet the target cleanliness, often expressed as an ISO 4406 code.
Drying and preservation. Systems are dried, blanketed with nitrogen or filled with preservative until start-up.
Oil flushing in more detail
Turbulence. Flushing flow is set so the oil stays turbulent (Reynolds number above about 4,000) in the largest pipe, often well above normal operating flow.
Temperature. Heating the oil lowers its viscosity, which raises turbulence and speeds the flush.
Filtration. Coarse and fine filters, down to a few microns, collect the dirt. An online particle counter shows when the target is reached.
Bypasses. Bearings, servo valves and other sensitive parts are bypassed with jumpers during flushing.
Chemical cleaning in more detail
Materials. Tanks, pumps and hoses must resist the acids at temperature: duplex, nickel alloys or lined steel.
Monitoring. pH, conductivity, temperature and dissolved iron show when each stage is complete.
Waste. Spent solutions are neutralised and disposed of under the site's environmental permit.
Where Tech Inc. equipment fits
Tech Inc. builds the heated high-velocity oil flushing skid, the chemical cleaning, pickling and passivation skid and the hydrotest and leak-test pump skid, as well as the hydraulic oil flushing unit.
Related reading
Sources
This note is general information. Cleaning and flushing procedures follow the project specification and the equipment makers' requirements.