At a glance. Water is almost incompressible, so a vessel filled with water stores little energy even at high pressure. That makes hydrostatic testing the standard way to prove pressure equipment, from gas cylinders and composite tanks in the factory to pipelines and plant piping before start-up.

The main tests

  1. Proof test. Pressure is raised to a set multiple of the working pressure and held; the item must not leak or deform permanently. Many cylinder standards measure permanent expansion in a water jacket.

  2. Leak or pressure-hold test. Pressure is held for a set time and the decay is recorded, corrected for temperature.

  3. Burst test. Pressure is raised until the item fails, to prove the design margin. This is a type-approval test.

  4. Pressure-cycling test. The item is filled and emptied thousands of times to prove fatigue life, sometimes at raised temperature.

Cylinder and tank standards (for CNG, hydrogen and other gases) set the pressures, hold times and cycle counts; test benches are programmed to the standard the maker works to.

What a factory test bench needs

  • A protected chamber with an interlocked lid, so burst and cycling tests run safely.

  • Intensifier pumps sized for both the volume to fill and the top pressure, often up to 1,000 bar or more.

  • Fast cycling valves and a manifold rated for millions of pressure reversals.

  • Calibrated transmitters and software that records pressure–time curves and writes the report.

What a field hydrotest skid needs

Pipeline and plant tests are done by pre-commissioning contractors on site. Their skids carry:

  • A fill pump for large volumes and a plunger test pump for the final pressure.

  • A break tank, test manifold, relief valves and calibrated gauges.

  • A recorder that produces the chart for the test package.

  • A lifting frame and a drive that suits the site: electric, diesel or compressed air.

Common problems

  • Air left in the system, which makes pressure unstable and stores dangerous energy.

  • Temperature changes mistaken for leaks; temperature must be recorded alongside pressure.

  • Uncalibrated gauges, which invalidate the test.