Sample Cylinders for Gas and LPG: Outage, Relief and Cleaning

Writer: Tech Inc
Tech Inc
5 days ago
2 min read

At a glance. Gas and liquefied-gas samples travel to the laboratory in stainless cylinders. For liquefied gases such as LPG the cylinder must never be liquid-full: an outage (ullage) tube leaves vapour space so the liquid can expand as it warms, and a relief device protects the cylinder if it does. Floating-piston cylinders keep the sample in a single phase instead. Every cylinder must be cleaned and dried before reuse, or the last sample contaminates the next.

Outage for liquefied gases

ASTM D1265 practice for LPG fills the cylinder through one valve and vents liquid through the outage tube until the liquid level reaches the tube end, leaving about 20% vapour space. The tube length therefore sets the outage, and it must match the method in use.

Relief devices

A rupture disc or spring relief valve set below the cylinder rating protects against overpressure from heating or overfilling. Discs are replaced after any burst and at set intervals; relief valves are tested.

Floating-piston cylinders

Where light components would partition between liquid and vapour, a floating-piston (constant-pressure) cylinder holds the sample in a single phase behind a piston pressurised with an inert gas. ASTM D3700 describes the practice for LPG.

Gas samples

Natural-gas samples taken to ISO 10715 practice use clean, dry cylinders, purged or evacuated before filling, with materials and internal coatings chosen so that sulphur compounds and mercury are not lost to the walls.

Cleaning between samples

Residues, especially heavy hydrocarbons, sulphur and mercury, carry over into the next sample. A cleaning cycle vents the cylinder, evacuates it, purges with heated nitrogen and repeats until a vacuum hold shows it is dry; cylinders that held liquids may need a solvent flush first. Recording each cycle gives the laboratory traceability.

Specification checklist

  • Gas or liquid, pressure and temperature, and components of interest

  • Volume, pressure rating and certification required

  • Outage tube length, relief type and valve type

  • Internal coating for reactive components

  • Cleaning method, cycle record and storage condition

Where Tech Inc. equipment fits

Sources

This guide is general information. Filling and handling follow the method and procedures the plant or laboratory applies.